Land Application System Treatment Improvements

Engineered by Still Waters Engineering for City of Camilla

Approximate Construction Cost $2 Million | Camilla, Georgia

Projected Timeframe: Spring 2024


This project primarily consists of the following: Installation of bypass pumping at Wastewater Treatment Facility with necessary bypass piping, demolition, and removal of two (2) existing Wastewater Lagoon Liner, removal of existing Geotextile Fabric and Under-Liner Ventilation Tubing and miscellaneous hardware. Installation of two (2) New 60 Mil HDPE Liner +/- 38,900 SY, removal and replacement of existing Baffle Curtain, pumping of existing sludge to a Belt Press for solid separation, disposal of sludge in approved landfill is required and all other appurtenances associated with a complete installation.